Fort Lauderdale Executive Airport Pavement Rehabilitation

FXE resurfacing project for Runway 9-27 is a required initiative outlined in the Airport's approved Airport Layout Plan (ALP). Resurfacing will take place on February 24, 2025, at 10:00 p.m. (local time) and will last 10 days. The work will be conducted in phases:  Phase 1: Four Days, February 24 -28  will begin on the eastern part of Runway 9. Phase 2: Two Days, February 28-March 3  will focus on the middle section of the runway, during which Runway 13-31 will be closed for the weekend, with both runways closed concurrently . Phase 3: Four Days, March 3-7.  will involve the